Fire Pump Tests
Fire Pump Testing (NFPA25 and NFPA20)
NFPA 25
currently requires annual performance testing of fire pumps. In a performance
test water is discharged and the net performance of the fire pump is analyzed
through a minimum of three flow points. NFPA 25 also requires non-flow testing
of fire pumps, were the fire pump is started and run for a time interval under
churn conditions. Currently weekly non-flow tests are required for diesel fire
pumps and monthly non-flow tests are required for electric fire pumps. The
non-flow test frequency remains an item that is debated during every NFPA 25
code cycle. NFPA 25 contains the testing requirements after acceptance. Two
different types of fire pump test are required: Performance Tests, and Non-flow
tests. In the 2007 edition of NFPA 25 Non-flow fire pump tests were required
weekly for both electric motor and diesel engine drive fire pumps. In the 2011
edition of NFPA 25, the required test frequency for electric motor drive fire
pumps was reduced to monthly. NFPA 20
contains the requirements for acceptance testing of fire pumps.
NON-FLOW TESTS
Although
NFPA 25 requires qualified personnel present at all pump tests, non-flow test
can be conducted automatically by new fire pump controllers. If the pump starts
automatically from a pressure drop, and completes the required run cycle, it
would pass, even if no one was there to observe the pump performance.
Non Flow
tests are required primarily to verify if the pump will start and run without
any apparent problems. Data for these tests can be on a paper check list and
require visual observation but no analysis. The data collected could be limited
to the date tested, or there might be a list of items that were visually
inspected. In a non-flow test the pump operates at churn for a minimum time of
10 minutes for electric motor pumps and 30 minutes for diesel engine fire
pumps.
The only
water discharged is a small quantity through the circulation relief valve in order
to keep the pump from overheating. NFPA 25 currently requires non-flow test to
be conducted weekly for diesel engine fire pumps and monthly for electric motor
fire pumps
PERFORMANCE TESTS
The
annual fire pump performance test is also an opportunity to determine if there
are any problems with the fire pump water supply, such as shut or partially
shut valves or obstructions from the water supply to the pump. If the test is
conducted with a flow meter, it usually will not be possible to identify
problems with the fire pump water supply NFPA 20
requires a performance test before pump acceptance.
NFPA 25
requires a yearly performance test in which performance readings are recorded
at Churn pressure - no flow, 100% of rated flow, and 150% of rated flow. Annual
flow testing is typically performed by qualified personnel who have a better
understanding of the fire pump operation.
Acceptable
test results can be up to 5% below the above figures due to possible
experimental error. Test results worse than 5% below the next figures (by NFPA20) should be
investigated and corrected.
FIELD ACCEPTANCE TESTS PROCEDURE
This activity
evaluates the pump performance over a range condition to ensure the pump will
perform as needed during an any emergency.
First, make
a visual check of the fire pump package. Verify the proper setting of pressure
switches and circuit breakers. Check for signs of overheating and excessive vibration. If hose and nozzles are
used, ensure they
are securely tied down. Ensure the hose valves are closed. If a flow meter is
used, verify the valve on
the discharge side of the meter is closed. Verify the pressure in the mains is
normal (i.e., jockey pump pressure)
to prevent water hammer.
After
starting the pump, verify that the relief valve (if provided) is not flowing
water, and then partially open one or two hose valves, or slightly open the
meter discharge valve. Check the general operation of the pump and driver.
Watch for vibration, leaks (oil or water), unusual noises, and general
operation; confirm slight water flow from packing glands.
If
a test valve header is used, regulate the discharge by means of the hose valves
and selection of
the nozzle tips. The play pipe has a removable 1 1⁄8-in. (28.6 mm) tip and,
when the tip is removed, the
play pipe has a 1 3⁄4-in. (44.4 mm) nozzle.
When a test meter is used, regulate the discharge valve to achieve
various flow readings
Test
the fire pump over its entire range of flow (0 to 150% of the rated capacity)
by controlling the quantity of water discharged. Start at low flow and
gradually increase it; starting the pump with hoses open
can cause cavitation. Important test points are at churn (no flow), rated
capacity, and 150% of rated
capacity. Two intermediate points should be taken to help develop the
performance curve.
Record
the following data at each test point: (a) Pump rpm (b) Suction pressure (c) Discharge pressure (d) Number and size of hose nozzles, pitot
pressure for each nozzle, and total gpm (L/min). For flow meter, record gpm
(L/min) (e) Amperes and volts (for electric motors drivers)
Analyze the data with the pump manufacturer submittal.
Throughout
the course of testing, start the pump 6 times manually and 6 times
automatically to verify prompt and smooth start-up at the required
pressures or flow. For electric motors, allow at least 5 minutes at full speed
after each start-up to allow motor windings to cool properly. For
electric motors > 200hp (150kW), no more than 2 starts in 10 to 12 hours
should be attempted, and a running interval of at least 15 minutes at full
speed should be allowed.
For
a diesel engine run the pump for at least 1 hour to verify smooth operation
without coupling failure or overheating. Check this by discharging at the 150%
point, allowing the engine temperature to stabilize,
and then run the pump for an additional 15 minutes.
After
the test, verify pressure in fire service mains is up to normal or up to jockey
pump pressure before the pump is returned to automatic service to prevent water
hammer. Verify all fire protection equipment is returned to the automatic mode
and fire protection control valves fully open. Only the valve to the test
header should remain closed
Comments
Post a Comment